DOT INTERSTATE WORK
- I-65 Reconstruction Project, Alabama DOT, Jefferson County, Alabama (2011, 7 mo.) 21 million
Was responsible for overseeing the project management of 2.3 miles of reconstruction work. Work included grading, drainage, pipe, asphalt pavement, concrete paving, its and lighting. 155,011 SY of 14” PCC was installed as well of 63,000 TN of bituminous concrete. Mainline and ramps, accelerated schedule finished early despite winter weather delays; maintained budget over, $ 200,000 in Bonus paid for early phase completion.
Award: AL- ACPA 2012 Silver Award - I-385, Laurens (2010, 8 mo.) 47 million
A typical 2-yr project accelerated to a 8 month schedule, including grading, drainage, pipe asphalt paving and concrete paving and Bridges. Completed early and under budget, full rehabilitation project, string-less paving with DBI. Had $50,000.00 disincentive/day $25,000.00 incentive received $625,000.00 BONUS
650,000 CY Grading, 75,000 tons Asphalt, 500,000 SY Concrete Paving, 110,000 SY of RCC Shoulders under IRI Spec
Award: SC- 2011 ACPA 2011 Silver Award, America’s Transportation Award, Placed 5th in “2011 Top 10 Roads” Roads & Bridges–Won Award for Erosion Control. 2010 Top Storm Water and Erosion Control Project South Carolina - I-520 Palmetto Parkway, South Carolina DOT, Aiken, South Carolina (2009) South Carolina first Design Build Project, 123 million
This project was a Greenfield Project which completed the I-520 loop around Augusta, Georgia and Akin South Carolina. This included Clearing, Grading, Drainage, Pipe, Asphalt Paving, Concrete Paving and Bridges. We were responsible for overseeing the project management of 6.5 miles of concrete pavement. The project is a controlled access four lane divided interstate facility including three interchanges and 13 bridges. Over 200,000 SY of PCC paving contained in 12 ramps and mainline on I-520 was completed in less than 6 months.
Award: This project was an ACPA National Pavement Award (Silver) winner for Divided Highways 2010.. Finished 3 months ahead of paving schedule, allowing early completion of entire project. - I-520/I-20 Palmetto Parkway, Georgia DOT, Augusta, Georgia (2009) 151 million
I-20/520 Augusta Georgia Design Build Total reconstruction Removal of existing Grading, Drainage, Pipe, Bridges, asphalt paving and concrete paving was responsible for overseeing the project management of over 250,000 SY of concrete pavement. The project is a controlled access four lane divided interstate facility including three Major interchanges and 13 bridges. Over 251,000 SY of PCC paving contained in 16 ramps and 25 mainline phases - I-75 Dooley County Joint Venture (2012) 52 million
24 miles 3 lane reconstruction including pavement removal, grading, drainage, pipe, asphalt paving and concrete paving. - I-85 Coweta and Fulton Projects (2006) 165 million
Reconstructed 8 lanes and shoulders with CRC Pavement Project included pavement removal, grading, drainage, pipe and Bridge repair. Oversaw this multiple staged project where 500,000 TNs of graded asphalt base, over 100,000 tons of asphalt and approximately 640,000 SY of CRC concrete pavement were installed. This project had 100,000 vehicles per day and had a major value engineering proposal in excess of $10 million - I-26 Charleston, SC (2007) 131 million
Complete reconstruction. Staged construction over 3 Years - I-29 Harrison County, IA (2008) 41 million
Total Reconstruction pavement removal, onsite crushing, Grading, Drainage, pipe and Concrete Paving. Exceeded Iowa DOT incentive in every paving category - I-80 Youngstown, OH (2004) 100 million
Complete reconstruction with 2500’ bridge over Youngstown water source, included 800,000 CY Grading, at completion received 2010 #4 Top Roads and Bridges in North America - I-76 Mahoning County, OH (2002) 12 million
6 miles total reconstruction Total Pavement Removal, Grading, Cement Stabilization, Wick Drains, and Concrete Pavement. 4 lanes and shoulders, received full ride bonus. - I-77 Summit, Cuyahoga, OH, 22 million
Various Asphalt and Concrete projects in Summit and Cuyahoga counties projects included total pavement restoration, grading, drainage, pipe asphalt paving and concrete paving. - I-480 Cuyahoga County (1998) 10 million
First Design/Build Asphalt Warranty in Ohio (7 years) needing no repair at the end of the Warranty period Project included Crack and Seating of existing Pavement, Grading, Pipe and Asphalt Paving.
MILITARY BASES
- Fort Benning Training Roads projects A and C, 8 million
24 + miles of 25’ wide concrete Tank Trails. Greenfield work, including Grading, Drainage, Pipe and Pavement. Both Projects won ABC excellence in construction awards. - Fort Stewart 2
Hardstand lots and roadways - Ft Bragg
Hardstand lots and roadways - Camp Lejeune
Removal of Pavement, Grading, Pipe, Lighting Base Work, and Concrete Paving for new and Replacement Concourse for tie-down of Helicopters
AIRPORT WORK
- Atlanta Hartsfield Taxiway Connectors, 22 million
First project in 10 years that involved closing of Runways, (had $6,000.00 a minute liquidated damages). No Damages Assessed. Installation of new Connectors including Grading, Drainage, Pipe, Base Stabilization and Concrete Paving. - Spartanburg Airport, 7 million
Replaced Concourse and Taxiways Complete removal and Replacement of Concourse including Grading, Drainage, Pipe, Base Stabilization and Concrete Paving. - FedEx Greensboro GSOH Mid Atlantic Hub, 16 million
New Facility installation including Grading, Pipe Base installation, Asphalt Paving, Concrete Paving and Building 310,000 SY Concrete Paving, Demanding P-501 Spec Placed concrete around 450 obstacles Schedule milestone were achieved, New FedEx Mid Atlantic Hub. - Hartsfield Concourse D
Concourse work, Removal and Replacement to accommodate New building Facility - Piedmont Airport
Installed new Taxiway Connector, Project included Grading, Drainage, Pipe, Base Stabilization and Concrete Paving. - Savannah Airport
Taxiway work, installed new Taxiway Connector, Project included Grading, Drainage, Pipe, Base Stabilization and Concrete Paving.
MILITARY AIRPORT WORK
- Blount Island (2009) 16 million
17 acres of Storage area for munitions loading including Grading, Drainage, Pipe, Sub-base installation and Concrete Paving - Goose Creek Weapons Station
Storage area for munitions loading, including Grading, Drainage, Pipe, Sub-base installation and Concrete Paving - Dobbins Air force Base, 15 million
Replaced Concourse and Taxiways Total Reconstruction, Removal of Existing Pavement, Grading, Pipe, Base Stabilization and Concrete Paving - Warner Robbins AFB
Replaced Concourse and Taxiways - McIntire JNT National Guard Base
Replaced Concourse and Taxiways, Total Reconstruction, Removal of Existing Pavement, Grading, Pipe, Base Stabilization and Concrete Paving - Beaufort AFB SC (2012) 67 million
New Concourse and Taxiways for tie down storage of F-18’s. Including Grading, Pipe, Base Stabilization and Concrete Paving
PRIVATE AIRPORT WORK
- Boeing Charleston Plant (2011) 28 million
New Concourse, Taxiway and Hardstand for construction of Boeing 787 Dreamliner. Including Grading, Pipe, Base Stabilization and Concrete Paving
RCC WORK
- I-385 28 MILES OF 10’ SHOULDER Ride Spec
- I-80 Truck stop Kenly NC 12 acres
BRIDGE WORK
- Bridge Jacking contractor
SPECIALTY WORK
- I-95 Weigh station
- I-75 CRC Rest Area Tampa Florida
Complete new rest Area project included removal of existing, grading, pipe, drainage, asphalt paving and CRC concrete paving. - Firestone Country Club Bridges